Structural works for safety enhancement of the “Cernobbio” tunnel through the construction of a new ventilation suspended ceiling and compliance of existing escape route.
MAIN WORKS:
- Consolidation works through cement grouting and resin grouting
- Restoration of reinforced concrete with high-strength mortars reinforced with mesh in basalt fibre
- Construction of works in reinforced concrete
- Installation of foundation bolts
| State |
Completato |
| Start Date |
19/09/2012 |
| End Date |
11/05/2014 |
| Client |
Anas S.p.A. – Department of road system of Milan |
| Planning Company |
Anas S.p.A. |
| Country |
ITALY, IT |
| Name and Composition of Consortium |
COLLINI LAVORI S.P.A. - Impresa Luigi Notari S.p.A. |
| Notari's Percentage Share |
30 % |
| Contract |
Structural works for safety enhancement of the “Cernobbio” tunnel through the construction of a new ventilation suspended ceiling and compliance of existing escape route |
| Work Type |
SOA "OG3" |