Execution of civil works regarding the entrance road to the valve chamber and the diversion canal at the hydroelectric power station of Doiras – Spain.
MAIN WORKS:
- Excavation by traditional method for the new access tunnel to the power station;
- Strengthening of ground through cement and resin injections and construction of tie-rods;
- Execution of sprayed concrete;
- Structures in reinforced concrete.
| State |
Completato |
| Start Date |
22/06/2006 |
| End Date |
28/02/2008 |
| Client |
Enel S.p.A. Divisione Generazione ed Energy Management - Ingegneria Civile e Idraulica Turin |
| Planning Company |
ENEL S.p.A. |
| Country |
SPAIN, ES |
| Work Type |
SOA “OG1” |