Civil engineering works for the consolidation of intake facilities and accessory work on the power plant of Traponzo (Viterbo)
MAIN WORKS:
Works mostly consisted in the maintenance of the inlet tunnel, particularly the strengthening of the vault, side walls and the foundation bed through the creation of steel ribs, electro-welded mesh and sprayed, smoothed and float-finished concrete.
In addition to the structural consolidation works, the foundation and the side walls inside the tunnel were redone through the creation of electro-welded mesh and thixotropic plaster, creation and recovery of plasters and cladding of the power plant and the construction of a steel bridge for vehicle transit
| State |
Completato |
| Start Date |
20/09/2012 |
| End Date |
07/11/2013 |
| Client |
Enel Green Power S.p.A. Construction Unit - Engineering & Construction Department |
| Planning Company |
Enel Green Power S.p.A. |
| Country |
ITALY, IT |
| Contract |
Civil engineering works for the consolidation of intake facilities and accessory work on the power plant of Traponzo (Viterbo) |
| Work Type |
SOA “OG5” |