Sardegnana Hydroelectric power plant – Dam of Lake Colombo (Bergamo): Structural and preservative renovation works.
MAIN WORKS:
- Waterproofing curtain using cement injection grouting through the perforations at the foot of the upstream side and crest of the dam
-Reinforcing of cutting areas of disconnect couplings through cement injections on the downstream side
-Creation of structural disconnect couplings using diamond wire for stone masonry cutting
-Reinforcement, waterproofing and coating of upstream side with osmotic mortar
| State |
Completato |
| Start Date |
14/06/2010 |
| End Date |
19/10/2012 |
| Client |
Enel S.p.A. - Unità Business di Sondrio Via Adamello 1 - 23100 Sondrio |
| Planning Company |
Enel S.p.A. - Unità Business di Sondrio |
| Country |
ITALY, IT |
| Contract |
Sardegnana Hydroelectric power plant – Dam of Lake Colombo (Bergamo): Structural and preservative renovation works |
| Work Type |
SOA "OG5" |