Civil engineering works for the demolition and reconstruction of the hydroelectric power station of Campagnola near Udine.
MAIN WORKS:
Demolition of masonry and structures in reinforced concrete cu m 8910.18
Piles of small diameter for foundations, underpinning of foundations and anchoring bolts ml 1614.00
Consolidation of land of any type and consistency by jet-grouting technique ml 3176.55
Reinforced structures in hardened concrete cu m 933.50
Installation of reinforcing structures and electro-welded mesh kg 90077.00
Plastering of structures, with mesh and concrete, on masonry sqm 413.98
State |
Completato |
Start Date |
01/12/2014 |
End Date |
29/02/2016 |
Client |
EDIPOWER (until 31/12/15), CELLINA ENERGY SRL (from 01/01/16 to 29/02/16) |
Planning Company |
Hydrodata S.p.A. |
Country |
ITALY, IT |
Contract |
Civil engineering works for the demolition and reconstruction of the hydroelectric power station of Campagnola near Udine. |
Work Type |
SOA “OG 1” |