Civil engineering works regarding the dam and the power tunnel for the hydroelectric power plant at Gallicano
MAIN WORKS:
- Execution of micropiles
- Redoing of drainage canals
- Perforations and injections
- Installation of tie-beams for road masonry reinforcement
- Works on intake structures
- Repair and waterproofing of concrete dam
| State |
Completato |
| Start Date |
09/03/2004 |
| End Date |
31/03/2005 |
| Client |
Enel Produzione S.p.A. - GEM Generazione |
| Planning Company |
Enel Power S.p.A. |
| Country |
ITALY, IT |
| Notari's Percentage Share |
100% |
| Contract |
Civil engineering works regarding the dam and the power tunnel for the hydroelectric power plant at Gallicano |
| Work Type |
SOA “OG8” |