Reconditioning of hydraulic structures at the hydroelectric power stations in the Udine area.
MAIN WORKS:
• Excavation
• Demolition and reconstruction of plaster
• Concrete demolition in hydraulic structures
• Concrete works in hydraulic structures
• Creation of passage cat. 1 with pre-compressed pre-fabricated buildings and metal structural work
State |
Completato |
Start Date |
30/01/2012 |
End Date |
03/04/2012 |
Client |
EdiPower S.p.A. |
Planning Company |
Studio Tecnico “Dott. Ing. Raganzini Paolo” |
Country |
ITALiA, IT |
Contract |
Interventi alle opere idrauliche presso le Centrali Idroelettriche del nucleo di Udine. |
Work Type |
SOA “OG8” |