Extraordinary maintenance of diverting canal for the power plants of Roccavione and Borgo San Dalmazzo (first stage systems).
Contract n. 5700008032 dated 04/06/2012
MAIN WORKS:
Cleaning, transport and deposal of material deposited inside the tunnel, stilling basin and forebay reservoir.
Milling of all cladding
Restoration with smoothed and float-finished cement mortars of side walls, vault and bed of diverting canal
Waterproofing of diverting canal and basins on both walls for an area of about 20000 sqm
Formation of joints.
Works were entirely executed in a tunnel over a total length of 3400 ml in one month including the opening of a window and the final reconstruction works at mid-tunnel.
State |
Completato |
Start Date |
24/09/2012 |
End Date |
26/10/2012 |
Client |
ITALGEN S.p.A. |
Planning Company |
Italcementi S.p.A. |
Country |
ITALY, IT |
Contract |
Extraordinary maintenance of diverting canal for the power plants of Roccavione and Borgo San Dalmazzo (first stage systems). |
Work Type |
SOA “OG1 – OG8” |