Works to the main sewer, south of the purifier plants (Castiglione S. Stefano) 4th intervention in the localities of Carraie – S. Pietro in Campo – Ravenna.
MAIN WORKS:
- Excavation and earthwork
- Supply and laying of PVC sewer pipes and stoneware pipe
- Soil investigations for existing pipelines, etc
- Electro-mechanical work
State |
Completato |
Start Date |
21/02/2005 |
End Date |
29/06/2007 |
Client |
Municipality of Ravenna (Road and Civil Infratructure Office) |
Planning Company |
SGI Studio Galli Ingegneria S.p.A. |
Country |
ITALY, IT |
Contract |
Works to the main sewer, south of the purifier plants (Castiglione S. Stefano) 4th intervention in the localities of Carraie – S. Pietro in Campo – Ravenna |
Work Type |
SOA “OG6” |