Planning and execution of works urgently required to strengthen the cladding of the Bricchetto railway tunnel.
MAIN WORKS:
Works concerned the planning and execution of the urgent works for the strengthening and consolidation of the cladding of the Bricchetto tunnel at “km. 94+769 along the Asti – Acqui line, regarding the mouth and the section included between caches 6 and 7 following several damages detected during extraordinary inspections of the lines carried on 26 Nov. 2013, 28 Nov. 2013 and 03 Dec. 2013.
In detail:
- Consolidation and restoration of the masonry at the mouth of the tunnel and on the wing walls through the injection of chemical mixtures
- Continuous radial riveting with GFRP bars
- Consolidation of tunnel railing by injection of chemical mixtures
- Demolition and cutting of vertical surfaces
- Installation of passive tie-rods
- Milling of masonry and installation of recessed steel ribs
- Execution of sprayed concrete
- Execution of drainage system with the laying of micro-slotted pipes for drainage
- Monitoring
- Casting of the tunnel invert
State |
Completato |
Start Date |
26/05/2014 |
End Date |
22/09/2014 |
Client |
RFI S.p.A. – Rete Ferroviaria Italiana Direzione Territoriale Produzione Torino Reparto Tecnico Gestione Lavori |
Planning Company |
Alpina S.p.A. |
Country |
ITALY, IT |
Contract |
Planning and execution of works urgently required to strengthen the cladding of the Bricchetto railway tunnel |
Work Type |
SOA “OG4” |