Waterproofing works on right crest of the Dam of Saretto for the Hydroelectric Power Station of Acceglio (CN)
MAIN WORKS:
• Drilling of holes, mostly in the area at the foot of the dam, to a maximum depth of 12-15 m
• Injection of mixtures: first phase with buffering function using bi-component colloidal mixtures; second phase including strengthening works and bonding with cement mixtures
• Execution of a series of georadar prospecting at the foot of the mountain and of the valley of the dam to localise previous drain channelling in the dam
State |
Completato |
Start Date |
06/09/2006 |
End Date |
03/11/2006 |
Client |
Enel Produzione S.p.A. Unità di Business Idroelettrica di Cuneo Via Roncata, 94 - Cuneo |
Planning Company |
Enel Produzione S.p.A. |
Country |
ITALY, IT |
Contract |
Waterproofing works on right crest of the Dam of Saretto for the Hydroelectric Power Station of Acceglio |
Work Type |
SOA “OS21” |