• Login
  • Register
  • ABOUT US
    • History
    • Mission and Values
    • Company
    • Code of Ethics
    • Sostenibilità aziendale
    • Politica Aziendale GDPR
    • Documents
    • References
  • SECTORS
    • Civil and industrial buildings
    • Road Works
    • Railways works
    • Dams and Hydraulic Structures
    • Foundation and Ground Consolidation
  • WORKS
    • Civil and industiral building
    • Road Works
    • Railways Works
    • Foundations and Consolidation
    • Dams and Hydraulic Structures
  • CERTIFICATIONS
    • Professional Qualifications
    • Quality, environment, safety
    • Other Certificates
  • CONTACT
    • Where we are
    • Branch Offices
  • WORK WITH US
  • ABOUT US
    • History
    • Mission and Values
    • Company
    • Code of Ethics
    • Sostenibilità aziendale
    • Politica Aziendale GDPR
    • Documents
    • References
  • SECTORS
    • Civil and industrial buildings
    • Road Works
    • Railways works
    • Dams and Hydraulic Structures
    • Foundation and Ground Consolidation
  • WORKS
    • Civil and industiral building
    • Road Works
    • Railways Works
    • Foundations and Consolidation
    • Dams and Hydraulic Structures
  • CERTIFICATIONS
    • Professional Qualifications
    • Quality, environment, safety
    • Other Certificates
  • CONTACT
    • Where we are
    • Branch Offices
  • WORK WITH US
  • Login
  • Register
Back

Albula Tunnel

Works - Works

Albula Tunnel

Client:

RhätischeBahn AG

Sector:

Works
Railways Works

generate pdf datasheet
download pdf
  • Description
  • Technical datasheet
Construction of new Albula Tunnel II - Plot 103: preliminary Albula Tunnel I + plot 103a: broadening of dugout.

MAIN WORKS:

Works were part of a larger project that included the construction of the new Albula Tunnel II for Ferrovie Retiche (RhB).

Works included:

The securing of the existing Albula tunnel I (length 5864 m), though static renovation works along the entire arch:
- Anchors (2.5 – 6m): 850 pcs
- Hilti HCCB anchors: 1600 pcs
-Shotconcrete d=5-20 cm: 14 000 m2
- Electro-welded mesh: 22 600 kg
-Masonry hydro-cleaning: 6 000 m2
- C25 concrete: 150 m3

The excavation (with explosives and by traditional method) of the mouths of the 12 new transversal connecting conduits between the existing tunnel and the new one: 2000 m3;

The laying of pipes for industrial and fire-fighting water along the entire length:
- Pipes in cast iron: 5 500 m
- Pipes in HDPE DN250: 350 m
Widening of the survey cave existing along the Albula tunnel II (about 2500,00 m3 of excavations with explosive and safety implementation).
State Completato
Start Date 12/05/2014
End Date 31/10/2015
Client RhätischeBahn AG
Planning Company IG PV Alvra
Country SWITZERLAND, CH
Name and Composition of Consortium Consorzio ARGE Bianco: Pizzarotti S.A. – NOTARI S.p.A.
Notari's Percentage Share 40%
Contract Construction of new Albula Tunnel II - Plot 103: preliminary Albula Tunnel I + plot 103a: broadening of dugout
Work Type SOA "OG4"

Description

Construction of new Albula Tunnel II - Plot 103: preliminary Albula Tunnel I + plot 103a: broadening of dugout.

MAIN WORKS:

Works were part of a larger project that included the construction of the new Albula Tunnel II for Ferrovie Retiche (RhB).

Works included:

The securing of the existing Albula tunnel I (length 5864 m), though static renovation works along the entire arch:
- Anchors (2.5 – 6m): 850 pcs
- Hilti HCCB anchors: 1600 pcs
-Shotconcrete d=5-20 cm: 14 000 m2
- Electro-welded mesh: 22 600 kg
-Masonry hydro-cleaning: 6 000 m2
- C25 concrete: 150 m3

The excavation (with explosives and by traditional method) of the mouths of the 12 new transversal connecting conduits between the existing tunnel and the new one: 2000 m3;

The laying of pipes for industrial and fire-fighting water along the entire length:
- Pipes in cast iron: 5 500 m
- Pipes in HDPE DN250: 350 m
Widening of the survey cave existing along the Albula tunnel II (about 2500,00 m3 of excavations with explosive and safety implementation).

Technical datasheet

State Completato
Start Date 12/05/2014
End Date 31/10/2015
Client RhätischeBahn AG
Planning Company IG PV Alvra
Country SWITZERLAND, CH
Name and Composition of Consortium Consorzio ARGE Bianco: Pizzarotti S.A. – NOTARI S.p.A.
Notari's Percentage Share 40%
Contract Construction of new Albula Tunnel II - Plot 103: preliminary Albula Tunnel I + plot 103a: broadening of dugout
Work Type SOA "OG4"

Note

generate pdf datasheet
download pdf

Impresa Luigi Notari is a public company limited by shares (S.p.A.) since 1986 and holds the following certificates: UNI EN ISO 9001:2015, BS OHSAS 18001:2007 and UNI EN ISO 14001:2015 issued by ICMQ

CONTACT DETAILS
VIA FELICE CASATI, 44
20124 Milan - ITALY
PHONE: 02.66.71.29.23 r.a.
FAX: 02.66.90.925
impresa.luiginotari@impresaluiginotari.com

© 2019 IMPRESA LUIGI NOTARI spa - PIVA: 08099180153

Restricted Area

You must be registered
to download the PDF datasheet

Forgot your password?

Not registered yet? Register

Register

Enter your email address and you will receive information on how to complete your registration

Password recovery

To receive your password please enter the email address provided during the registration process